01-04-2021 We were tasked with the decommissioning and conversion of a large 50,000 egg-laying unit. In the first phase, we removed all non-metals from the site. This included fabricating a bespoke unit capable of coiling 3,600 Metres of PVC belts.
Second phase we removed any re-useable parts, and finally we removed all access platforms a
01-04-2021 We were tasked with the decommissioning and conversion of a large 50,000 egg-laying unit. In the first phase, we removed all non-metals from the site. This included fabricating a bespoke unit capable of coiling 3,600 Metres of PVC belts.
Second phase we removed any re-useable parts, and finally we removed all access platforms and mezzanine floors.
This site has now being converted to a free-range egg unit. Morris Maintenance hold the contract for the preventative maintenance on site.
“We have been using Morris Maintenance for over 4 years for various repair and improvement works, we have appointed Jonny and his team to implement the PPM schedules for our multiple free-range units. we also rely on morris maintenance for their speedy breakdown attendance- Mike, Farm manager
01-02-2024 The Ice Co are the largest manufacturer of ice cubes in Europe. We have held the planned maintenance contract with them for over 6 years, with regular reviews and amendments to adapt to changes on site.
Much of the work is carried out "out of hours" to work around the busy production schedules.
"Morris Maintenace provide for ou
01-02-2024 The Ice Co are the largest manufacturer of ice cubes in Europe. We have held the planned maintenance contract with them for over 6 years, with regular reviews and amendments to adapt to changes on site.
Much of the work is carried out "out of hours" to work around the busy production schedules.
"Morris Maintenace provide for our business a flexible and cost-effective contract solution. We are a very seasonally based business that during peak times needs to perform at its optimum in order to deliver our customer needs. Having reliable plant is critical, hence why we use Morris Maintenance"- Lee, operations director
01-02-2020 Burton Agnes Renewables are a "gas to grid" biogas production site. A large anaerobic digester is fed with agricultural by-products and energy crops to produce biogas.
We were appointed in October 2018 initially to cover breakdowns and soon after took over the "in-house" 7- & 30-day PPM schedules.
Since this time, we have modifi
01-02-2020 Burton Agnes Renewables are a "gas to grid" biogas production site. A large anaerobic digester is fed with agricultural by-products and energy crops to produce biogas.
We were appointed in October 2018 initially to cover breakdowns and soon after took over the "in-house" 7- & 30-day PPM schedules.
Since this time, we have modified the schedules to include items that had been overlooked. Over the past 12 months, we have implemented a CMMS & created an inventory of spare parts and specialist suppliers.
“We appointed Morris Maintenance initially to provide engineering support, in particular breakdown cover. However, that role has evolved over time and since working with Morris Maintenance we have experienced improvements in fixed asset availability which has allowed us to improve plant utilisation. I can't praise Jonny and his team enough for the impact they have had at Burton Agnes” - Andy, Site Manager